Pragati Maidan Bridge | Systra India

Pragati Maidan Bridge

Indraprastha - Bara - khamba Road-Dwarka(from Delhi metro line 3), 32.1 km long, is mainly built on viaduct, which makes the metro line architecturally unique in India. The Barakhamba Road-Indraprastha section includes the first extradossed bridge in India which is also the second one of its kind in the world built over a railway crossing.

The viaduct, being constructed above 5 railway lines, without any interruption to their traffic. The DMRC, SYSTRA and the Indian Railways imposed very strict safety standards to ensure that no incident would happen and interrupt the daily traffic of more than 200 trains.

Inaugurated on November 11, 2006, the Pragati Maidan Bridge has scored a record in construction time, at an extremely competitive cost. Works were carried out night and day to meet with the execution plan.

SYSTRA India was in charge of all studies in civil engineering, system interface as well as construction supervision, which included:

  • Design study of foundations
  • Study of piers and pylons
  • Seismic study
  • longitudinal and transverse deck analysis
  • Drainage
  • Geometry control
  • Technical specifications
  • Maintenance manual and an instrumentation of the bridge

ESSENTIAL

  • Extradossed Bridge built over a railway crossing
  • Part of Delhi metro Line 3,

Pragati Maidan Bridge

  • Bridge length: 196.3 m (with a central span of 93 m long)
  • Pylons height: around 25 m above the ground
  • Level of tracks: between 9.7 m and 16.95 m above the level ground
  • Track alignment: curved with a radius of 302.05 m
  • Record time : 9 months of construction
  • More than 230 workers involved in the construction
  • Status : Completed

CLIENT

Delhi Metro Rail Corporation Ltd.

Go Back

Read Also

HSR : Pune-Mumbai-Ahmedabad Corridor

The project includes a feasibility study of 640km of high speed rail corridor, with trains running a(...)

Mumbai Trans-Harbour Link

The proposed Mumbai Trans Harbour Link (MTHL) has been planned to facilitate decongestion(...)

Mumbai Metro Line 1

Mumbai metro line 1 is an elevated corridor of 11.5km with 12 stations (from Versova, via Andheri to(...)

Navi Mumbai Metro

Navi Mumbai metro Rail project includes a construction of an elevated line of 117.3km. The aims is t(...)

SYSTRA MVA Consulting (India) Private Limited, Vatika Mindscapes, Mathura Road, Faridabad T.(+91) 129 668 5600

Contact